Anthony Allega Cement Contractor, Inc.

Repair Runway 01-19

Dover Air Force Base, Dover, Delaware

DoverAnthony Allega Cement Contractor, Inc. has been subcontracted by Versar Inc. in the amount of $28,873,805 to perform concrete paving activities associated with the replacement of Runway 01-19 and portions of Runway 14-32 at Dover Air Force Base. This project includes the replacement of 10,000 lineal feet of concrete pavement along Runway 01-19 as well as 1,700 lineal feet of concrete pavement along the intersection of Runway 14-32 and Runway 01-19. In addition, Taxiways Bravo, Charlie, Delta, Echo, and Foxtrot will also be rehabilitated as part of this project.

Allega is paving this project dual lanes at 37’ wide with an average of 4,000 cubic yards of concrete per day. In order to maximize efficiency and production on the Dover Air Force Base project, Allega has mobilized two on-site concrete batch plants. Working in conjunction with each other, they will place over 165,000 cubic yards of concrete in order to manage the large daily production needs.Dover

Allega’s scope of work on this project entails over 246,000 square yards of 15” and 20” concrete finished pavement and over 257,000 square yards of 5” drainage layer concrete. The project commenced in February 2015 and is currently scheduled for completion in December 2016.

Dover

>> Back to list of Current Projects