END ERT COMMENT OUT -->

ODOT Project 500-10

Project Title: ODOT Project 500-10

Project Location: IR-90 West

Project Owner: ODOT

Completed under budget and on time


IR-90 West

In June of 2011, Anthony Allega Cement Contractor, Inc. completed work on ODOT Project 500-10 located in Cuyahoga County, Ohio on Interstate Route 90 in the City of Cleveland. The $1.7 million project was completed on-time and under budget. Work was completed in four phases and included the repair and replacement of the median wall in both the eastbound and westbound directions.

A highlight of the project was the minimal impact to traffic on Interstate 90 and the motoring public. Short term temporary closures were utilized and crews worked late/early hours to avoid any disruption in daily traffic flow. Another highlight was a new concrete barrier wall slip-form machine that Allega has devised and was utilized for this project. The machine was able to maneuver around light poles and median inlets while staying on the shoulder for construction.

The project’s success can be attributed to the partnership between Allega and The Ohio Department of Transportation, and the tireless efforts of the field crews performing the work.


>> Back to list of Completed Projects