ODOT Project 100054

Project Title: ODOT Project 100054

Project value: $31,600,000

Project Location: Interstate Route 90 in Lake County, Ohio

Project Owner: ODOT

Completed on schedule


Anthony Allega Cement Contractor, Inc. was awarded this project for a bid cost of $31,600,000. Located in Lake County, Ohio on Interstate Route 90 in Leroy and Madison Townships, this seven mile long project included the widenings of the State Route 528 ramps beginning at Ford Road, heading east towards State Route 534, and ending at the Ashtabula County Line. The scope of this project involved a full depth pavement removal and replacement with asphalt pavement of both westbound and eastbound lanes. In addition, the State Route 528 ramps were removed and replaced with concrete pavement and widened at the 528 Intersections. Cement stabilized of the subgrade was performed throughout the entire job, including the new ramps.

Beginning in late April of 2010, this project was scheduled for completion in June 2012, slightly longer than two years. There were four phases that made up the entirety of this project. Work commenced with Phases 3 and 4, which involved the westbound lanes. These two phases had an interim completion date of October 30, 2010. Work on the eastbound lanes (Phases 1 and 2) began in the spring of 2011 and was completed by the scheduled date of October 30, 2011. Final cleanup work such as final striping, some landscaping and punch list work finished during the 2012 season.


>> Back to list of Completed Projects